Since October, all government invested housing construction and municipal infrastructure projects have implemented “separation of evaluation”! Another province issued a document


The bid evaluation committee shall strengthen the review of the bidder’s credit status and performance ability, and give priority to innovation, green and other evaluation factors around the requirements of high-quality development

.

From October 2021, the implementation of “separation of evaluation” in project bidding will be officially launched

.

For projects that use the evaluation separation mechanism to randomly determine the bid winning candidates, a total price contract shall generally be implemented

.

Guide the tenderee to scientifically formulate the “separation of evaluation” scheme, introduce the “pass system” and “limited quantity system” in the bid evaluation stage, specify the review standards, and strengthen the analysis of technical scheme, the evaluation of quotation rationality and the judgment of risk in the bid evaluation stage

.

Whether to adopt remote bid evaluation shall be determined by the tenderee independently

.

In November 2020, Guangzhou Municipal Bureau of housing and urban rural development issued the guidelines on exploring the operation of “separation of evaluation” of housing construction project bidding (Trial)

.

In July 2020, Guangdong Provincial Department of housing and urban rural development issued the implementation opinions on deepening the bidding reform in the field of housing construction and municipal infrastructure projects, implemented 16 reforms in the three links of bidding, bid evaluation and supervision, and tried out the “separation of evaluation” system

.

Timely adjust and publish the reference standards for abnormally low bidding prices for housing construction, rail transit, municipal infrastructure and other projects, resolutely put an end to bidding at low prices, and severely crack down on illegal acts such as bid encirclement and collusion

.

Regions that have not yet implemented the “separation of assessment” system should learn from the experience of regions that have implemented it and formulate detailed rules for “separation of assessment” in combination with local conditions, so as to promote the pilot of “separation of assessment”

.

the content only represents the author’s personal views and is edited and sorted by “construction economy and management” (the graphic copyright belongs to the original author)

. Halfen Channel

Strengthen the supervision during and after the “separation of evaluation” project, and severely crack down on illegal acts in the process of bid evaluation and award

.

In March 2021, Anhui Provincial Department of housing and urban rural development and other 17 departments jointly issued the twelve opinions on continuously promoting the development of the construction industry, which made it clear that the separation of evaluation should be the first to be implemented in government investment projects, and the tenderee should, on the basis of the qualified bid winning candidates recommended by the bid evaluation committee, follow the principles of science, standardization and transparency,   The bid winner shall be determined independently, and the bidding method shall be specified in the bidding documents

.

The bid evaluation methods and standards are consistent with those that do not adopt the “evaluation separation” method

.

In 2021, Hebei Provincial Department of housing and urban rural development issued the implementation plan for the pilot work of “separation of evaluation” in the bidding of housing construction and municipal infrastructure projects: the “separation of evaluation” was implemented for all housing construction and municipal infrastructure projects invested by the government

.

In April 2021, Jiangsu issued the implementation opinions on promoting the “separation of evaluation” in the bidding of housing construction and municipal infrastructure projects invested by state-owned funds in the whole province (Exposure Draft): the “separation of evaluation” method is adopted in the bidding of design, construction and supervision of housing construction and municipal infrastructure projects invested by state-owned funds in the whole province

.

At present, Hebei, Sichuan, Henan, Guangdong, Jiangsu and other places have issued documents to promote the “separation of evaluation” of project bidding

.

In December 2020, Sichuan Provincial Development and Reform Commission, the Department of housing and urban rural development and other six departments jointly issued the notice on implementing the separation mechanism for the evaluation of bid winning candidates in the whole province, and decided to implement the separation mechanism for the evaluation of bid winning candidates in the whole province

.

2

.

It is not allowed to directly select potential bidders, bid winning candidates or bid winners by means of drawing lots, lottery numbers, rate bidding, etc

.

Support Luoyang to carry out the pilot reform in the field of bidding for housing construction and municipal infrastructure projects, explore and implement measures such as separation of evaluation, simplification of bidding preconditions, cancellation of prior filing of bidding documents, optimization of bid evaluation guidelines, establishment of post bid evaluation and social supervision mechanism, improve the supervision level of project bidding, and strive to form replicable and popularized practical experience

.

1

.

On August 2, Anhui Provincial Department of housing and urban rural development issued the notice on carrying out the pilot work of “separation of evaluation” in the bidding of housing construction and municipal infrastructure projects in the province, requiring the General Contracting Bidding and construction bidding of housing construction and municipal infrastructure projects invested by the government to implement “separation of evaluation”

.

The competent housing and urban rural construction departments at or above the local level shall try out the “separation of evaluation” system, and the bid evaluation committee shall be responsible for reviewing the bid documents, providing technical advice and suggestions on the bidder’s technology, quality, safety, construction period control ability and other factors, and recommending non ranked bid winning candidates; The tenderee is encouraged to establish and improve internal control procedures and decision-making restraint mechanism, establish a bidding committee, and the bidding committee will select the winning bidder from the winning candidates

.

In March 2021, Zhejiang Provincial People’s government issued the opinions on Further Strengthening the legal governance in the field of engineering construction project bidding, steadily promoted the reform of “separation of evaluation” in bidding, and encouraged the “separation of evaluation” in the whole process of engineering consulting bidding in survey, design and the whole process; Explore the reform of “separation of evaluation” in the field of construction and general contracting; Support qualified regions to carry out regional comprehensive pilot projects of “separation of assessment”

.

The material of this article comes from the websites of Anhui Provincial Department of housing and urban rural development, local housing and urban rural development departments, Jianshe Tong, etc

.

All cities (prefectures) shall formulate detailed rules for the implementation of the evaluation separation mechanism

.

In June 2020, Henan Provincial Department of housing and urban rural development issued the implementation plan for special rectification of engineering construction industry in Henan Province

.

3

.

If necessary

.

All localities are encouraged to implement “separation of evaluation” according to the situation

.

If the total investment of the project is less than 30 million yuan (excluding 30 million yuan) and the total investment of a single project in the bundled approval project is less than 10 million yuan (excluding 10 million yuan), the tenderee is encouraged to adopt the evaluation separation mechanism

.

The tenderee can select a certain proportion of bidders (no less than 3) from all bidders who have passed the compliance review by random selection, and select the best candidates for winning the bid according to their qualification performance and credit rating

.