Construction project completion acceptance super whole process complete version


d

.

b

. Cast In Loop

The construction unit shall obtain the filing form for completion acceptance of housing construction projects and municipal infrastructure projects from the filing authority

.

The public security fire control institution shall complete the examination of the fire control design of the construction project submitted for examination within the specified time limit

.

The construction unit shall submit the filing form for completion acceptance of housing construction projects and municipal infrastructure projects in quadruplicate and the materials specified above to the filing authority for filing with the official seal of the unit and the signature of the project leader of the unit

.

Complete technical archives and construction management data; 3

.

Elevator acceptance certificate issued by the supervision station

.

Complete the design documents of housing construction project and various contents agreed in the contract; 2

.

C

.

After accepting the acceptance declaration, the public security fire control institution shall organize the acceptance within 10 days, and issue the opinion on fire control acceptance of construction engineering within 7 days after the acceptance

.

After reviewing the engineering technical data, the supervision station evaluates the project and issues the construction safety evaluation of construction project (the construction unit sends the engineering technical data to the supervision station for review 15 days in advance), The supervision station shall return the return form of project completion quality and safety management data to the construction unit within 5 days

.

obtain special acceptance documents such as planning, public security, fire protection, environmental protection and gas engineering

.

The following documents: (1) construction license( 2) Review comments on construction drawing design documents( 3) Project quality assessment report( 4) Engineering survey and design quality inspection report( 5) Relevant quality inspection and functional test data of municipal infrastructure( 6) Planning acceptance approval documents( 7) Fire control acceptance documents or permit documents( 8) Environmental protection acceptance documents or permit documents( 9) Elevator acceptance permit and divisional acceptance documents issued by the supervision station( 10) Gas engineering acceptance documents( 11) Guangzhou construction project quality warranty( 12) Other documents required by regulations, rules and regulations

.

2

.

Failure to reply within the specified time limit is consent

.

General works shall be inspected at least once before completion, and key works and works with automatic fire-fighting facilities shall be inspected at least three times.

.

5、 Filing procedures for completion acceptance of construction projects 1

.

2、 Conditions for completion acceptance of housing construction project 1

.

4、 Materials prepared by the construction unit for operation filing of construction project completion acceptance filing: 1

.

Engineering technical data (20 working days before acceptance); Supervision company (within 5 working days) (2) supervision company: prepare project quality assessment report (3) survey unit: prepare quality inspection report (4) design unit: prepare quality inspection report (5) construction unit: A

.

After completing the audit, the auditors shall put forward audit opinions in time, and a special person shall conduct general technical review

.

3

.

8

.

The construction auditor shall regularly supervise and inspect the construction in progress and make inspection records

.

The personnel participating in the site selection, scheme feasibility demonstration or preliminary design review meeting organized by the competent construction department shall fill the opinions in the record form of preliminary review opinions of construction projects

.

7、 Construction project completion acceptance procedure 1

.

For the acceptance of key projects and projects with automatic fire-fighting facilities, an acceptance organization with the participation of acceptance, construction review, supervision, war training and other personnel shall be established, and the acceptance work plan shall be formulated

.

There is a project warranty signed by the construction unit

.

Quality qualification documents signed by survey, design, construction, supervision and other units; 5

.

6

.

When accepting the application for fire acceptance of construction project, the public security fire department shall check the following data: (1) application form for fire acceptance of construction project( 2) Technical test report of building fire-fighting facilities( 3) Review opinion on fire protection design of construction engineering and relevant reply documents( 4) As built drawings( 5) Qualification certificate of construction and installation unit of fire engineering, construction, installation and commissioning records, relevant certificates of fire products, factory certificates, records of concealed works, records of design and construction changes, etc( 6) Various fire safety management systems, fire safety management organizations and list of fire system operation management personnel; 2

.

3、 Supervision of construction project completion acceptance (operated by the supervision station) 1

.

7

.

Project completion acceptance (organized and implemented by the owner, with the participation of engineering survey, design, construction, supervision and other units): (1) contractor: a

.

5

.

2

.

After being approved and signed by the supervision unit, the “project acceptance report” shall be submitted to the owner (general contractor), and then the owner (general contractor) shall organize the design, construction, supervision and other units to carry out the completion acceptance of construction projects, For the intermediate completed single project that has gone through the handover procedures, the completion acceptance will not be repeated( 2) The owner (general contractor) shall organize the survey, design, construction, supervision and other units to check the project according to the completion acceptance procedures, make the acceptance conclusion and form the “project completion acceptance report”, and the responsible persons of all parties involved in the completion acceptance shall sign on the completion acceptance report and affix the official seal of the unit

.

3

.

1、 Preparation for completion acceptance of construction project and pre acceptance of project completion (organized by the supervision company and participated by the owner and the Contractor): after the project is completed, the supervision engineer shall review the data and conduct on-site inspection according to the application form for completion pre acceptance of unit project submitted after the Contractor’s self inspection and acceptance; The project supervision department puts forward written opinions on the existing problems, issues the supervision engineer’s notice (Note: fill in when necessary), and requires the contractor to rectify within a time limit; After rectification, the Contractor shall prepare the completion acceptance report of construction project according to the requirements of relevant documents, submit it to the supervising engineer for inspection, and submit it to the owner after the project director signs his comments

.

Submit the project technical data and the review sheet of project completion quality and safety management data to the supervision station 15 days in advance (the supervision station shall return the return sheet of project completion quality and safety management data to the construction unit within 5 days)

.

The filing authority shall sign the filing opinions (seal) on the filing form for completion acceptance of housing construction projects and municipal infrastructure projects within 15 working days after receiving and verifying the filing materials, and the construction unit, construction unit, supervision station and filing authority shall each hold one copy

.

From the date of receiving a full set of design drawings, the review opinions on fire protection design of construction projects shall be issued within 10 days for general projects and 20 days for key projects and projects with automatic fire protection facilities; If it is necessary to organize expert demonstration, it can be extended to 30 days

.

After the review opinions on fire protection design of construction projects for key projects and projects with automatic fire-fighting facilities are issued, the construction reviewers shall urge the construction unit and the design unit to implement the review opinions and feed back in time

.

6、 Main contents of organizing on-site acceptance (1) the whole construction project has been completed according to the design requirements and meets the specified completion acceptance standards of construction projects

.

There are mobilization test reports of main building materials, building components, fittings and equipment used in the project; 4

.

Project acceptance personnel shall not be less than 2

.

After receiving the written notice of project completion acceptance (the construction unit shall notify the supervision station of the acceptance time, place and list of acceptance teams in writing 7 days before the project completion acceptance, and attach the project quality acceptance plan), the supervision station shall review according to the review form of construction project completion acceptance conditions, and review the organization form, acceptance procedures Carry out on-site supervision on the implementation of acceptance standards, and issue opinions on construction project quality acceptance

.

4

.

b

.

the contractor prepares the construction project completion acceptance report to the owner of the supervision company

.

7 days before the completion acceptance of the project, the supervision station shall be informed in writing of the acceptance time, place and list of acceptance teams

.

Construction project completion acceptance report 2

.