[jianjiantong] all 8 bidding units have abandoned their bids! Project flow standard!


Lifting Anchor

does not comply with the clarification addendum of the bidding document (I) the response deviation list of the bid document specified in Article 20 of the addendum does not comply with the clarification addendum of the bidding document (I) Article 20 of the addendum stipulates that the response deviation list of the bidding document of Shanghai Mitsubishi Elevator Co., Ltd.

Review of other bidders (except the bid winning candidates), name of the bidder, bid price (yuan) or bid rejection basis clause (terms of evaluation factors and evaluation standards in the bid evaluation method of the bidding document on which the bid document is determined to be unqualified), reviewed bid price (yuan) or reasons for bid rejection (the specific fact that the bidding document is determined to be unqualified shall not be simply expressed as failure to respond to the substantive contents of the bidding document, problems somewhere, etc.) the comprehensive evaluation score or remarks include the daily maintenance base price of the elevator during the operation and maintenance service period of Otis electromechanical Elevator Co., Ltd., the component level special repair base price of the escalator and elevator The quotation of medium repair base price is lower than the cost price, the daily maintenance base price of elevator during operation and maintenance service period, the component level special repair base price of escalator and elevator The quotation of medium repair base price is lower than the cost price by 0.00 Otis Elevator (China) Co., Ltd.

The list of deviation from the response of the bidding document of Shanghai Mitsubishi Elevator Co., Ltd.

The response deviation list of the tender document does not comply with the clarification and addendum of the bidding document (I) Article 20 of the addendum stipulates that the response deviation list of the bid document of Hangzhou Theo Elevator Co., Ltd.

bid document response deviation list does not comply with Chapter VI bid document format VIII of bidding document (II) response to bidding document The deviation list specifies that the response deviation list of the bidding document does not comply with Chapter VI bidding document format VIII of the bidding document.

0.00 other contents to be publicized are not the same.

Other materials (II) response of the bidding document Deviation from the provisions of the schedule, the quotation of the component level special base repair price of the escalator during the operation and maintenance service period of Hangzhou Theo Elevator Co., Ltd.

Publicity of bid evaluation results of elevator and escalator equipment procurement, installation, operation and maintenance service project of Chengdu rail transit line 19 phase II and line 27 phase I Project (flow of bid), Eight units rejected the bid.

does not comply with Chapter VI form VIII of the bidding document (II) the response of the bidding document, the list of deviation from the response of the bidding document specified in the list of deviation does not comply with Chapter VI form VIII of the bidding document (II) the response of the bidding document Deviation list stipulates that 0.00 Schindler (China) Elevator Co., Ltd.

The quotation of medium repair base price of operating elevator of Hitachi Elevator (China) Co., Ltd.

is lower than the cost price, the quotation of the component level special base repair price of the escalator during the operation and maintenance service period is lower than the cost price, the quotation of the operation and maintenance service period of Kangli Elevator Co., Ltd., and the quotation of each base price are lower than the quotation of the operation and maintenance service period of the cost price All the base price quotations are lower than the cost price by 0.00.

the response deviation list of the tender document does not comply with the clarification and addendum of the bidding document (I).

The operation and maintenance service period quotation of Kangli Elevator Co., Ltd.

During the operation and maintenance service period of Hitachi Elevator (China) Co., Ltd., the daily maintenance base price quotation of escalators and elevators is lower than the cost price; The special repair and intermediate repair of operating parts failed to quote according to the tax rate specified in Article 18 of the addendum (I) of the clarification and addendum of the bidding document, and did not accept the correction of the price by the bid evaluation committee..

The name of the bidder of Tisheng elevator (China) Co., Ltd.

During the operation and maintenance service period, the daily maintenance base price quotation of escalators and elevators is lower than the cost price by 0.00.

and all base price quotations are lower than the cost price All base price quotations are lower than the cost price by 0.00.

is inconsistent with the business license.

Jianzhong001 source: Rail City, Henan Provincial Department of housing and urban rural development and network Summary recently, the bid evaluation results of Chengdu Rail Transit Line 8 phase II, line 13 phase I, line 10 phase III, line 17 phase II, line 18 phase III, line 30 phase I and rail transit Ziyang line project elevator and escalator equipment procurement, installation and operation and maintenance service project (flow bid) were released, According to the announcement, there are no bid winning candidates, and all 8 bidding units reject the bid.

does not comply with the clarification and addendum of the bidding document (I) Article 20 of the addendum stipulates that the response deviation list of the bidding document does not comply with the clarification and addendum of the bidding document (I) Article 20 of the addendum stipulates that 0.00 Schindler (China) During the operation and maintenance service period of Elevator Co., Ltd., the daily maintenance base price quotation of escalators and elevators is lower than the cost price.

The reasons for the rejection are different.

Review of other bidders (except the bid winning candidates), name of the bidder, bid price (yuan) or bid rejection basis clause (terms of evaluation factors and evaluation standards in the bid evaluation method of the bidding document on which the bid document is determined to be unqualified), reviewed bid price (yuan) or reasons for bid rejection (the specific fact that the bidding document is determined to be unqualified shall not be simply expressed as failure to respond to the substantive contents of the bidding document, problems somewhere, etc.) the comprehensive evaluation score or remarks include the daily maintenance base price of the elevator during the operation and maintenance service period of Otis electromechanical Elevator Co., Ltd., the component level special repair base price of the escalator and elevator The quotation of medium repair machine is lower than the cost price, the daily maintenance base price of elevator during operation and maintenance service period, the special repair base price of escalator and elevator at component level The quotation of medium repair machine price is lower than the cost price by 0.00.

exceeds the control price specified in item 3.2.1 of Chapter II “instructions to bidders”, and the quotation of medium repair base price of operating elevator exceeds the control price specified in Chapter II “instructions to bidders” The control price specified in item 3.2.1 is 0.00.

quotation during operation and maintenance service period, each base price quotation is lower than the cost price quotation during operation and maintenance service period, and each base price quotation is lower than the cost price by 0.00 Otis Elevator (China) Co., Ltd.

Tags:

Related Post

The “hard standard” of one household and one house in rural areas has been issued, and all illegal buildings will be demolished, except forThe “hard standard” of one household and one house in rural areas has been issued, and all illegal buildings will be demolished, except for

Lifting Clutches Please pay attention to it. Before reading this article, please click on the “Gushi native village” and click “attention”. It’s free subscription. Then click the top right corner