Sprint for “construction engineering” daily practice before the second construction examination (11)


general contractor C.

The stirrup limb distance in the densified area of column stirrup shall not be greater than 200mm at level I, 250mm at level II and III and 300mm at level IV.

The technical department of the construction unit shall organize the professional technicians of the construction technology, safety, quality and other departments of the unit to review the special construction scheme prepared.

Preparation and approval of construction organization design of unit works: the construction organization design of unit works shall be prepared by the project leader, attended by all managers of the project management department, reviewed by the competent department of the construction unit, and approved by the technical director of the construction unit or its authorized technicians.

Level 3 should not be greater than 250 , D.

[single choice] a.

the project technical director of the construction unit organizes professional review – signature of the technical director of the construction unit – Review and signature of the chief supervision engineer; C.

So the answer to this question is C.

So the answer to this question is option a.

According to the seismic requirements, the stirrup limb distance in the dense area of column stirrup is () mm.

Therefore, choose a for this question.

For the floor type steel pipe scaffold project with a height of more than 60m that needs to be accepted according to the regulations, which unit’s relevant personnel need to organize the acceptance.

The success of each practice will be reflected in the score incisively and vividly.

answer analysis: this question examines the general regulations on fire protection at the construction site.

Xiaobian has prepared five daily practice questions (with answer analysis) for you every day.

the project technical director of the construction unit organizes professional personnel to review – the signature of the technical director of the construction unit – the review and signature of the owner’s project director or the chief supervision engineer # correct answer: a # answer analysis: this question examines the approval process of the special scheme.

construction unit correct answer: B.

answer analysis: 3.

[single choice] a.

The above is the “dry goods” carefully prepared by Weilang education for you.

The setting of living quarters must meet the fire prevention requirements, and open fire heating is strictly prohibited in the dormitory.

 。.

answer analysis: this question examines the management of the construction organization design of the unit project.

level 1 should not be greater than 150 , B.

[single choice] A.

In 2022, the examination of “construction engineering” for grade II constructor is divided into single choice questions, multiple topics and example questions of constructor case.

the chief supervision engineer; C.

1.

You can get the relevant reference materials of the constructor for free.

electric heater C.

For more information, please continue to pay attention to Wei Lang education.

design unit D.

professional contractor B.

2.

So the answer to this question is option C.

Foot Mounted Anchor

After passing the examination, it shall be signed by the technical director of the construction unit.

Level 2 should not be greater than 200 , C.

the technical department of the construction unit organizes professional review – signature of the technical director of the construction unit – Review and signature of the chief supervision engineer; B.

[single choice] A.

open fire D.

level 4 should not be greater than 350 , correct answer: C , answer analysis: this question examines the configuration requirements of column stirrups.

He will accompany you to prepare for the exam step by step.

At least every other longitudinal reinforcement should be restrained by stirrups or tie bars in two directions; When the tie bar composite hoop is adopted, the tie bar should be close to the longitudinal reinforcement and hook the stirrup.

the technical director of the professional contractor organizes professional review – signature of the technical director of the professional contractor – Review and signature of the chief supervision engineer Signature D.

The competent department of the enterprise; correct answer: A.

water heater C.

the technical director of the construction unit; B.

I hope to help you on the road of “textual research”.

5.

The special scheme that does not need to be demonstrated by experts shall be submitted to the supervision unit after being reviewed and qualified by the construction unit, and the chief supervision engineer of the project shall review and sign.

It is forbidden to use () for heating in the living area on site.

If the general construction contract is implemented, the special scheme shall be signed and determined by the technical director of the general contractor and the technical director of relevant professional contractors.

Come on together.

4.

correct answer: C.

The competent department of the construction unit; d.

Special construction scheme without expert demonstration, the approval process is ().

Get more information: scan the QR code below and leave a private message.

() [single choice] A.

The approval of the construction organization design of the unit project is ().

air conditioner B.

Tags:

Related Post