Procedures for issuance of construction permit (parallel approval of quality supervision and safety supervision)


5); 4 Notice of Zibo Municipal People’s Government on Printing and Distributing the Implementation Plan for the Reform of the Approval System of Zibo’s Optimized and Enhanced Engineering Construction Projects (ZZF [2019] No.

There are many data uploaded in this link, please ensure that the original is scanned and the data is complete.) 4、 Application Document 1 Application Form for Construction Permit of Construction Engineering (parallel approval of quality and safety supervision) – prepared according to the single building; 2 Land use approval procedures; 3.

8).

This link needs to retrieve and enter the drawing review number, and the construction unit shall timely urge the drawing review unit to enter the drawing review information into the approval system after the completion of drawing review; 2.

If there is no account, register first.

18 of the Ministry of Construction on June 25, 2014, amended on September 28, 2018); 3 Article 6 of Shandong Provincial Measures for the Administration of Housing Construction and Municipal Engineering Construction Permit (LJF [2018] No.

Construction project planning permit or rural construction planning permit (attached with general layout); 4.

2、 Scope 1 Various housing construction, urban municipal engineering and rural construction projects above designated size (collectively referred to as construction projects); 2 Housing construction projects refer to the construction, decoration and fitment of various types of housing buildings and their ancillary facilities, as well as the installation of their supporting lines, pipelines and equipment; Municipal engineering refers to the civil engineering, pipeline and equipment installation of urban roads and bridges, tunnels, public transport, rail transit, water supply, drainage, gas, heat, sanitation, sewage treatment, garbage treatment, flood control, underground public facilities and other ancillary facilities; Rural construction projects above designated size refer to rural construction projects for schools, kindergartens, health centers and other public welfare undertakings, and rural construction projects with an investment amount of more than 300000 yuan or a building area of more than 300 square meters (excluding residential projects with 2 floors or less built by farmers themselves).

The construction unit logs in.

(1.

Shuttering Magnet

After saving the information, you can fill in the subsequent phase, which does not need to be submitted for approval; In addition, when adding “unit project name”, the project name should be added, such as “XXX construction project 1 # building”.

After the registration, call the window telephone: 6195399.

After the completion of the filling, submit it.

According to the requirements of ZJF [2002] No.

Procedures for issuance of construction permit for construction projects in Zhoucun District (parallel examination and approval of fire control and quality and safety supervision) I Approval basis 1 Article 8 of the Construction Law of the People’s Republic of China (passed on November 1, 1997 and amended on April 23, 2019); 2.

Article 4 of the Administrative Measures for Construction Permit of Construction Projects (Order No.

Rural construction projects refer to housing construction and rural infrastructure projects built on rural collective construction land; 3 Construction projects with an investment of less than 1 million yuan or a building area of less than 500 square meters may not apply for a construction permit.

The construction, design, survey and supervision units should do a good job in the municipal bureau filing of the units and personnel, otherwise the units and personnel cannot be retrieved in the system.) 4 Fill in the information related to Single Body Registration.

In this link, it is necessary to determine the construction unit and the supervision unit, and it is recommended that the construction unit carry out the bidding or direct contract awarding work of the construction and supervision unit in advance; 2.

3、 Handling process (the certificate can be issued after the commitment materials are complete) 1 Log in to the “Online Office Hall of Zibo Housing and Urban Rural Development Bureau” (website: http://60.210.113.36:8006/ZiBoHuiYuanShenBao/Login.aspx ); (1.

Call the window telephone: 6195399 to complete the review, and then proceed to the subsequent link; 3 Fill in and submit the relevant information of “bid section registration”, and upload the “Notification of Award of Construction and Supervision Units” or “Registration Form of Direct Contracting of Construction and Supervision Units”.

In this link, you need to fill in and submit the basic information of the project, the civil air defense construction situation, upload the project approval document, and the scanned copy of the original civil air defense approval document.

After the approval, log in and use it.

After completion of the filling, call the window telephone: 6433356 to complete the review and continue the follow-up process; (1.

Shandong Province Construction Project Construction Drawing Design Document Review Certificate (for special construction projects requiring fire protection design review, an Application Form for Fire Protection Design Review of Special Construction Projects and an electronic version of construction project fire protection design drawings and general layout plan shall also be provided (Each page shall be affixed with the seal of approval and the qualification seal of the design unit within the period of validity, including the complete set of drawings of architecture, water, electricity and heating, and the drawings of outdoor pipe network, if the supporting facilities are provided with fire pump room and fire pool).

13 document, the review organization of construction drawings in our district is: Zibo Luzhong Survey and Design Review Consulting Center, contact person: Jiao Yudong, contact number: 13953339196..

2.

Before logging in, set the browser according to the requirements of “Browser Settings Before Login” in the login interface.) 2 First fill in the “event handling” – “project information registration”.

5 Fill in and submit the “construction permit (quality and safety supervision, civil air defense, fire protection)”, complete the relevant information and upload the scanned copy of the original data, call the window telephone: 6195399, after the review is completed, bring the paper data to the window to print the license.