Industry trends ┃ Shanghai safety and quality supervision station requires the city’s construction sites to do a good job in typhoon “CANDU”


As the first responsible person of the project, the project leader of the construction unit and the chief supervision engineer of the supervision unit shall do a good job in self inspection and self correction of flood and typhoon prevention on the construction site in advance, and focus on the formulation of emergency plan for flood and typhoon prevention on the construction site, the construction of emergency team Implementation of material and equipment reserves and emergency shelters; Focus on the investigation of hidden dangers in key parts such as foundation pit, hoisting machinery (especially strengthening the inspection of tower crane), scaffold, temporary electricity, temporary house, on-site drainage, enclosure, gate, fence, underground space and the safety of personnel on duty at the construction site.

571), in order to effectively do a good job in the flood and typhoon prevention of the city’s construction sites and ladder adding projects during the typhoon and ensure the safety of people’s lives and property, Here are the following tips on relevant matters: first, raise awareness and keep ready for war at all times.

4、 Pay attention to the Taiwan flood and scientifically implement the response of flood and typhoon prevention at all levels     All units (departments) shall pay close attention to the Taiwan flood information, timely respond to and start the emergency plan according to the early warning information of the municipal meteorological department, make preparations for comprehensive shutdown and personnel risk avoidance transfer, strictly implement the relevant epidemic prevention and control requirements during the transfer and resettlement, and strengthen the supervision of construction sites, ladder adding projects under construction Typhoon prevention and supervision of small projects, and consolidate the safety production responsibility of enterprises.

The project participants shall further optimize and improve the emergency plan for flood and typhoon prevention on the basis of the emergency rescue plan for construction safety production of construction sites, ladder adding projects and small projects according to the characteristics of flood and typhoon prevention in the city this year and in combination with the actual situation of the construction site; Relevant departments shall strengthen the supervision and reminder of street and town small project management, make every effort to prepare for emergency rescue, establish a multi-party cooperation and efficient flood control linkage mechanism, and all flood control material reserve units shall strengthen the dispatching management of flood control materials to ensure that they can be transferred and used.

Take corrective measures in time to completely eliminate the hidden dangers.

Ringlock Scaffolding System Parts

All units (departments) shall immediately and comprehensively carry out hidden danger investigation.

3、 Improve the emergency plan and strengthen the emergency management of emergencies.

All relevant units (departments) should further raise awareness, based on the most serious storm impact that typhoon “CANDU” may bring to Shanghai, resolutely overcome paralysis and fluke mentality, keep a clear mind, establish a leading group for flood and typhoon prevention, and improve the post responsibility system for flood and typhoon prevention, Implement the responsibility of flood and typhoon prevention, always tighten the string of flood and typhoon prevention, adhere to the bottom line of “no death, less injury and less loss”, and make the most comprehensive preparations for flood and typhoon prevention.

Attachment: scan the QR code on the left of the flood and typhoon prevention checklist of the construction site under construction or click“.

If it is difficult to rectify at the moment, emergency measures shall be implemented according to the requirements of one place and one scheme to ensure safety.

2、 Implement responsibilities and comprehensively carry out hidden danger investigation.

Source of this article: the party construction of safety and quality supervision, in accordance with the spirit of the video conference of the municipal flood control headquarters on September 12 and the requirements of the emergency notice on effectively doing a good job in the defense of Typhoon “CANDU” this year (hjefl [2021] No.

In case of an emergency, emergency measures shall be taken at the first time, and the event situation shall be reported in time to ensure that the emergency is responded, handled and reported at the first time.

5、 Reasonably arrange and implement the flood and typhoon prevention duty system     During the typhoon affected period, all units (departments) involved in the construction shall strengthen the organization and leadership, strictly enforce the work discipline, implement the emergency duty responsibilities, timely submit information, strengthen the duty preparation force, strictly implement the 24-hour duty system, and ensure smooth information communication.

Tags:

Related Post

Professor Meng Yang from Shandong Architecture University came to Zibo housing and Urban Rural Development Bureau to make a technical report on green building materialsProfessor Meng Yang from Shandong Architecture University came to Zibo housing and Urban Rural Development Bureau to make a technical report on green building materials